In the short period of its existence, the 4 Waters company has acquired references in preparation of Design Documentation for Municipal and Industrial wastewater treatment plants, drinking water treatment plants, supervision of civil and mechanical works and provision of different technical consultancy services in regards to mechanical and civil works and technical control of technical documentation.

 

Year Location Client Description
2018 Vrsac, Serbia Aqualia infraestructuras doo Beograd-Vračar Water treatment plant for municipality of Vršac, capacity 300l/s

Tasks: Preparation of Operation and Maintenance Manual

Notes: Project funded by EUD

2018 Sremska Mitrovica, Serbia Studio Structura, Belgrade Installations for technical gases (He, O2, N2), cooling water and water demineralization plant with DW installations in MODINE plant, Sremska Mitrovica

Tasks: Design for Execution of Works

2018 Belgrade, Serbia Mašinoprojekt Kopring, Belgrade Waste water treatment plant for “Nikola Tesla” airport, capacity 6.000PE

Task: Conceptual design of the WWTP with MBR technology and water re-use

2018 Belgrade, Serbia PC Art, Belgrade Reconstruction of the public underground garage “Pionirski park”

Tasks: Design for Execution of Works for civil, mechanical and electrical part

2018 Vrsac, Serbia Aqualia infraestructuras doo Beograd-Vračar Water treatment plant for municipality of Vršac, capacity 300l/s

Tasks: Consultancy services – providing engineering services as Construction manager of the Contractor

Notes: Project funded by EUD

2018 Kragujevac, Serbia FCA (Fiat Chrysler Automobiles) Serbia WWTP “Katak I”, “Katak II” and “Katak III”

Tasks: Engineering services – providing of service for regular and extraordinary maintenance of waste water treatment plants in FCA Kragujevac

2017-2018 Kostolac, Serbia P2M Berlin GmbH Supervision of Construction and Commissioning of the New WWTP in TPP Kostolac B in the Republic of Serbia

Tasks: Consultancy services – providing engineering services as Team Leader of FIDIC Engineer Project team

Notes: Project funded by EUD

2017 Danilovgrad Montenegro Evergreen for Development B.V. Central municipal waste water treatment plant for city of Danilovgrad, capacity 6.000PE

Tasks: Consultancy services – support in tender preparation, complete tender design, contact with equipment suppliers, CAPEX and OPEX assessment

2017 Soko Banja, Serbia Hidromreža, Zaječar Reconstruction and expansion of Sokobanja DWTP

Tasks: Civil (Construction) design for Flocculator, Tube settler and Fast filters and Civil (Construction) design for reconstruction of Slow Filters

2017 Tivat, Montenegro Lindner doo, Tivat Porto Montenegro facilities on cadastral plots 1-5b and 1-14

Tasks: calculation services, the back checking of BoQs from the main design, for execution of works

2017 Prague, Czech Republic Lindner doo, Belgrade ˝The Oaks˝ luxury apartments complex

Tasks: calculation services, the back checking of BoQs from the main design, for execution of works

2017 Belgrade, Serbia Mace doo, Belgrade Feasibility study for Thermal power plant GACKO II

Tasks: Technical control of Feasibility study

2017 Šid, Serbia Ehting doo, Beograd Remediation and sanitation of landfill in “Victoria Oil” Complex in Šid

Tasks: Process and Mechanical Design for sanitation

2017 Vrsac, Serbia Aqualia infraestructuras doo Beograd-Vračar Water treatment plant for municipality of Vršac, capacity 300l/s

Tasks: Stress analysis of piping and piping supports design

2017 Belgrade, Serbia Voding-92 Pressure boosting drinking water pump station “Boleč” and parts of roads U1 and U2 with belonging infrastructure for IKEA center Belgrade

Tasks: Technical control of design for construction permit

2017 Raška, Serbia Evergreen for Development B.V. Central municipal waste water treatment plant for city of Raška, capacity 16.500PE

Tasks: Consultancy services – support in tender preparation, complete tender design, contact with equipment suppliers, CAPEX and OPEX assessment

2016 – 2017 Turkey Louis Berger “Technical Assistance for Assessment of Drinking Water Resources and Treatment Plants in Turkey”:

Tasks: Conceptual designs for improvement and new drinking water plants in multiple cities in Turkey

– Reconstruction and expansion of Aksaray DWTP, capacity 500l/s

– Design for New Hacibaba DWTP in Gazientep, capacity 2000l/s

–  Expansion of  Beypazari DWTP, capacity 60l/s

–  Reconstruction of Isparta DWTP, capacity 1000l/s

–  Reconstruction and expansion of Eskisehir DWTP, capacity 3700l/s

–   Design for Keban DWTP, capacity 14l/s

Notes: Project funded by EC

2016 Radovis, Macedonia Aquafluent (for WTE) Preliminary and Detailed design for Central Waste Water Treatment Plant for city of Radovis, Macedonia, capacity 25.000 PE

Tasks: Mechanical Design

2016 Kicevo, Macedonia Aquafluent (for WTE) Preliminary and Detailed design for Central Waste Water Treatment Plant for city of Kicevo, Macedonia, capacity 32.000 PE

Tasks: Mechanical Design

2016 Strumica, Macedonia Aquafluent (for WTE) Preliminary and Detailed design for Central Waste Water Treatment Plant for city of Strumica, Macedonia, capacity 54.000 PE

Tasks: Mechanical Design

2016 Prahovo, Serbia Faculty for mining and geology – Belgrade Waste water transport system from Fluoric acid production plant to new landfill for phosphoric plaster, and pumping station for drainage water (capacity 210m3/h), ELIXIR Prahovo, Serbia

Tasks: Mechanical Design

2016 Novi Sad, Serbia Evergreen for Development B.V. Waste water treatment plant for meat processing plant NEOPLANTA, Novi Sad

Tasks: Consultancy services – support in bid preparation, contact with equipment suppliers, CAPEX and OPEX assessment